1、
项目净现金流=-333+100/1.15+150/1.15^2+200/1.15^3=-1.11868167995
按照15%的资本成本,项目净现金流量大于零,应该进行投资
2、
333=100/(1+IRR)+150/(1+IRR)^2+200/(1+IRR)^3
插值法求IRR

朱飞飞老师 解答

2023-11-18 13:38

同学,不好意思,第一问写的结论不对,应该是这样
项目净现金流=-333+100/1.15+150/1.15^2+200/1.15^3=-1.11868167995
按照15%的资本成本,项目净现金流量小于零,不应应该进行投资


插值法:
IRR=15%

100/(1+IRR)+150/(1+IRR)^2+200/(1+IRR)^3=100/1.15+150/1.15^2+200/1.15^3=331.88
IRR=14%
100/(1+IRR)+150/(1+IRR)^2+200/(1+IRR)^3=100/1.14+150/1.14^2+200/1.14^3=338.13
(15%-IRR)/(15%-14%)=(331.88-333)/(331.88-338.13)
IRR=0.1482

上传图片  
相关问题讨论
学员您好,净现值=-500%2B200/1.09%2B240/1.09^2%2B100/1.09^3%2B160/1.09^4=76.0558(万元)。
2023-11-29 15:37:55
同学,你好, 项目的净现值=-500%2B200/1.09%2B240/1.09^2%2B100/1.09^3%2B160/1.09^4=-500%2B200/1.09%2B240/1.09^2%2B100/10.9^3%2B160/1.09^4=-1.08531096548
2023-11-16 19:08:20
同学您好:现在为您解答
2023-11-11 00:02:02
你好 净现值=100/(1%2B15%)%2B150/(1%2B15%)^2%2B200/(1%2B15%)^3-333=-1.12,净现值小于0,不可行 100/(1%2Bi%)%2B150/(1%2Bi%)^2%2B200/(1%2Bi%)^3-333=0 irr=14.82%,小于资本成本15%,项目不可行
2023-11-06 21:13:31
你好 计算过程如下所示 npv=36000*(P/F,11%,1)%2B44000*(P/F,11%,2)%2B38000*(P/F,11%,3)-44000*(P/F,11%,4)%2B81000*(P/F,11%,5)-110000 =5014.49 应该
2020-07-15 10:43:20